Scheduling under Linear Constraints

Published 29 Oct 2015 in cs.DS | (1510.08551v1)

Abstract: We introduce a parallel machine scheduling problem in which the processing times of jobs are not given in advance but are determined by a system of linear constraints. The objective is to minimize the makespan, i.e., the maximum job completion time among all feasible choices. This novel problem is motivated by various real-world application scenarios. We discuss the computational complexity and algorithms for various settings of this problem. In particular, we show that if there is only one machine with an arbitrary number of linear constraints, or there is an arbitrary number of machines with no more than two linear constraints, or both the number of machines and the number of linear constraints are fixed constants, then the problem is polynomial-time solvable via solving a series of linear programming problems. If both the number of machines and the number of constraints are inputs of the problem instance, then the problem is NP-Hard. We further propose several approximation algorithms for the latter case.

Citations (12)

Summary

No one has generated a summary of this paper yet.

Paper to Video (Beta)

No one has generated a video about this paper yet.

Whiteboard

No one has generated a whiteboard explanation for this paper yet.

Open Problems

We haven't generated a list of open problems mentioned in this paper yet.

Continue Learning

We haven't generated follow-up questions for this paper yet.

Authors (3)

Collections

Sign up for free to add this paper to one or more collections.